# What does NEC4 ECC clause 60.1(10) mean?

An instructed search may support a compensation event if the contractual conditions are met.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 14 October 2026 · About 2 min readShare

## The answer

An instructed search for a Defect may support a compensation event where the actual conditions are met. The outcome of the search and compliance with prior inspection or covering-up requirements can matter. Check the corresponding contract provision rather than relying solely on the ECC clause 60.1(10) label.

Keep the instruction, locations opened, inspection attendance, photographs and recorded findings. Distinguish no Defect found from a disputed or incomplete search. Preserve any notice you were required to give before the work was covered, together with service evidence.

Value opening-up, inspection assistance and reinstatement on the applicable assessment basis only after the relevant entitlement is established. If some locations contain Defects and others do not, identify the facts and allocation separately. A search instruction is not itself proof that every opening and repair cost is payable.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) records the search instruction, findings and associated resource costs separately from unrelated work. For a contested position: To have a refused event tested against the clause it falls under and pressed to implementation, see our [NEC compensation event recovery](<https://www.quantsurv.com/claims/nec-compensation-event-recovery>) service.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)