# How does NEC4 ECC clause 15 work?

Early warnings identify matters that could affect cost, time or performance so the parties can manage them.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 14 October 2026 · About 1 min readShare

## The answer

Early warnings identify matters that could affect cost, time or performance so the parties can manage them. Give the required warning promptly through the agreed communication system and record mitigation decisions; a warning does not replace a separate compensation event notification. These clause numbers refer to NEC4 ECC guidance; apply the corresponding provisions of your actual contract rather than substituting parties into the main contract. Record the operative form, amendments, notice requirements and service evidence. We prepare the cost records and assessment; your representative deals with contractual interpretation and dispute procedure, and your appointed planner supplies any required delay analysis.

For what an early warning notice is and when to give one, see [what an NEC early warning notice is](<https://www.quantsurv.com/compensation-events/faq/early-warning-notice>).

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) maintains the risk and action record without treating an early warning as a substitute for a separate event notice.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)