# What happens if I miss the 8 week deadline for a compensation event?

You may lose the change to your price and dates, but whether you do depends on your contract's exact wording, its exceptions and the facts.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

You may lose the change to your price and dates, but whether you do depends on your contract's exact wording, its exceptions and the facts. The commonly cited eight-week period concerns NEC ECC; NEC ECS uses seven weeks, subject to the edition, actual amendments and exceptions. A missed applicable notification period can remove the change to price and dates.

But do not assume 8 weeks applies to every NEC contract. Amendments often change the period or the exceptions. Equally, do not assume every instruction is automatically exempt.

So act now. Put the event, the date you first became aware, any instruction or notification relied on, the parties and the dates in one list. Set the actual clause beside it. Keep all the correspondence, and get advice quickly on the rule that applies, any exception and what you can still do. Do not treat the event as automatically lost, or as automatically worth a discounted deal.

For the ECC/ECS distinction, awareness trigger and actual exceptions, see [how NEC4 clause 61.3 works](<https://www.quantsurv.com/compensation-events/faq/nec4-clause-61-3-notifying-a-compensation-event>).

Our [NEC compensation event recovery](<https://www.quantsurv.com/claims/nec-compensation-event-recovery>) can compare the event, the notification record and the contract that applies.