# What is an NEC early warning notice, and when must I give one?

An early warning notice flags anything that could add cost, cause delay or affect how the finished works perform, and you give it straight away.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

An early warning notice flags anything that could add cost, cause delay or affect how the finished works perform, and you give it straight away. The early warning notice comes from NEC contracts, and in the NEC4 main contract it sits in clause 15. On an NEC contract you give early warnings to the other party, and it must give them to you.

The duty starts as soon as you become aware of the matter, not once you know what it will cost. Give it in writing, through the communication system your contract names. Say what the matter is, when you found it, and what it could affect: the price, the dates or the finished works. The matter then goes on the early warning register and to an early warning meeting. There, both sides look for ways to avoid or reduce its effect.

An early warning is not a claim and not an admission. Nor is it a compensation event notification, and one never does the job of the other. If the matter turns out to be a compensation event, notify it separately and on time. A missing warning may affect the assessment under the applicable clause and decision procedure, by reference to what a timely warning could have avoided; it is not an automatic deduction for every late warning.

JCT forms can also impose notification requirements, including early notification in relevant 2024 forms. Check the selected contract and its distinct delay and loss-and-expense notices. Our NEC compensation-event process setup service keeps a live early warning register beside your notification routine.

For the clause itself, the register and the meetings, see [how NEC4 clause 15 works](<https://www.quantsurv.com/compensation-events/faq/nec4-clause-15-early-warnings>).

Our [Construction contract management](<https://www.quantsurv.com/quantity-surveying#client-types>) assigns an owner and follow-up actions to early warnings while tracking separate notification duties.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)