# Is a compensation event deemed accepted if nobody replies?

Silence can have contractual consequences only after the required steps and periods. Check the actual NEC form, edition, amendments and the specific reply mechanism before treating an event or quotation as accepted.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

Silence can have contractual consequences only after the required steps and periods. Check the actual NEC form, edition, amendments and the specific reply mechanism before treating an event or quotation as accepted. The process can differ between a decision on a notified event, a quotation and an assessment. Establish the communication served, the reply due and any required notice of failure.

Some standard NEC mechanisms provide a further period after a valid notice of failure, but do not copy a period from an ECC main-contract explanation into an ECS subcontract. Read the actual clause and amendments. Keep the notices and service records together.

Also check what the consequence establishes. Treating an event as a compensation event is different from accepting a particular price and time assessment. Our NEC compensation event recovery service checks the event file and applicable procedure before recommending the next action.

For the clause behind the first step, see [how NEC4 clause 61.4 works](<https://www.quantsurv.com/compensation-events/faq/nec4-clause-61-4-project-manager-decision-on-a-notified-event>).

For help reviewing unanswered events and the applicable follow-up procedure, see our [NEC compensation event recovery](<https://www.quantsurv.com/claims/nec-compensation-event-recovery>) service.