# What is a compensation event under NEC4?

A compensation event is an event your NEC4 contract lists as one that can change your price, your dates, or both.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

A compensation event is an event your NEC4 contract lists as one that can change your price, your dates, or both. The actual form, edition, options, Contract Data and amendments determine the event and procedure. Main-contract and subcontract periods differ: the commonly cited ECC notification period is eight weeks and the ECS period seven, subject to the actual terms and exceptions. Record the event and evidence promptly, notify through the required route and build the quotation from the applicable cost rules. Early warnings, event notifications and quotations perform different functions. Your appointed planner assesses any required programme effect; your representative confirms disputed contractual questions.

### The compensation event procedure

Scroll across to read all columns.

The compensation event procedure
| Stage | What to check |
| --- | --- |
| Notification | Responsible party, actual trigger, period and service |
| Decision | Applicable grounds and reply period |
| Quotation | Instruction, cost rules, programme inputs and deadline |
| Missing reply | Relevant reminder mechanism and further period |
| Assessment and implementation | Grounds, figure, dates, dispute rights and register entry |

For the full NEC4 list of events, see [what NEC4 clause 60.1 means](<https://www.quantsurv.com/compensation-events/faq/nec4-clause-60-1-compensation-events>).

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) links the event to the notification, quotation and assessment process required by the NEC agreement.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)