# Is bad weather a compensation event under NEC4?

Under the NEC4 ECC weather mechanism, specified measurements are compared with the contract's recorded threshold. A wet day alone is not enough; check the actual contract, location, measurement and assessment period.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

Ordinary bad weather is your risk under NEC4, however frustrating it is. The weather compensation event, clause 60.1(13) in the NEC4 main contract, is a test of records, not of opinion. The Contract Data names a weather station, the measurements that count and the source of the weather data. The measurements are things like rainfall or days with snow lying.

You compare one calendar month's record at that station with the once-in-10-years value for the same month. Only if the record is worse is there an event. Even then, you are paid only for the difference between the actual weather and the once-in-10-years weather, not for every wet day.

Check when awareness of the event starts the notification period under your actual contract. Do not assume the clock waits for published monthly records: flag and notify a potentially qualifying event promptly as required, then supplement the measurement evidence. So record the weather days on site, and get the station's monthly records as they are published. Ask for the once-in-10-years values at the start of the job. Your contract may change this clause or name a different station, so check yours.

On a JCT job, exceptionally adverse weather usually gives you time but not money. Our NEC compensation event recovery service tests a refused weather event against the records and the clause.

For the clause wording and how the assessment is limited, see [what NEC4 clause 60.1(13) means](<https://www.quantsurv.com/compensation-events/faq/nec4-clause-60-1-13-weather>).

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) gathers the specified weather evidence and affected-work records for the contractual assessment. For a contested position: To have a refused weather event tested against the records and pressed to implementation, see our [NEC compensation event recovery](<https://www.quantsurv.com/claims/nec-compensation-event-recovery>) service.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)