# Remeasure their figure before you argue with it

Check significant quantities and rates against the drawings and records before answering a claim. Focus on differences that materially affect the amount.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## Why

Rates get argued in meetings. Quantities get taken on trust, because measuring is slow. So a claim against you often carries generous quantities. The other party's site team measured the defect, the rework or the damaged area, and nobody on their side checked. A 10% overstatement in the biggest head is worth more than any argument about rates. Finding it also changes how the rest of their claim is read: it stops being taken as a measurement. Argue only the principle, however well, and their figure stays the only measured number on the table.

## How do I do it?

1.  Rank the heads of the claim by value, and pick the 3 or 4 that carry most of it.
2.  Remeasure a sample of each from the drawings, your handover records and your photos, without working from their figure.
3.  Compare your sample with the claimed quantity, and work out the percentage difference.
4.  Remeasure the whole head where the difference is bigger than rounding would explain.
5.  Record the sample, the method and the result, so you can show the check itself.

Our [Claim assessment and response](<https://www.quantsurv.com/claims#client-types>) tests the claimed quantities and rates against the work and records before a response is prepared.

[Browse dispute resolution and defence in the Library](<https://www.quantsurv.com/library#topic-defence>)

[Browse the Library](<https://www.quantsurv.com/library>)