# When does a claim against me become a dispute?

It can become one once the claim is rejected, or left unanswered for long enough, but exactly when is a legal question.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 12 October 2026 · About 2 min readShare

## The answer

A claim can become a dispute once it is rejected or left unanswered for long enough, but exactly when is a legal question. In everyday terms, a claim is a demand for something the other side says it is owed, and a dispute is a disagreement that has not been settled. The exact point matters because it decides when either side can refer the matter to adjudication, so check it with your solicitor.

In practice, it runs like this. Read the substance of each communication. A reservation may be only a warning, but a claim or dispute can concern liability, time or another entitlement before money is quantified. A priced schedule makes the financial position clearer; it is not the sole test. A claim that has been rejected, or left unanswered for long enough, may already be a dispute that either side can refer to adjudication.

So log every allegation and figure you receive, answer each one in writing, and note any urgent date.

Our [Claim assessment and response](<https://www.quantsurv.com/claims#client-types>) service tests a claim made against you and builds your answer; [Claim risk review and evidence process setup](<https://www.quantsurv.com/claims#client-types>) sets up the records that answer one before it is made.