# How do I assess a construction defects or remedial cost claim?

Separate responsibility for the alleged defect, the work needed to address it and the amount claimed. A repair invoice alone does not establish all three.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 3 min readShare

## Before you start

Collect the claim, specification, design responsibilities, inspection and handover records, photographs, notices and proposed repair costs. Identify the response deadline and arrange technical or legal input where needed.

## Step-by-step guide

1.  ### 1. Establish the alleged defect and responsibilities
    
    Compare the allegation with the agreed specification, design duties and supplied or installed work. Keep disputed responsibility separate from the repair price. NEC's guidance on [defining and managing defects](<https://www.neccontract.com/news/defining-and-managing-defects-in-ecc-and-liability-for-not-correcting-them>) explains why main-contract and subcontract obligations must be considered separately.
    
2.  ### 2. Check the necessary repair and procedure
    
    Use an appropriate technical specialist for disputed cause or remedial scope. Check notices, access and correction procedures. Distinguish necessary repair from changed specifications, betterment or unrelated work.
    
3.  ### 3. Assess the supported cost
    
    Reconcile the quantities, rates, invoices and resource records to the identified repair. Separate access and associated costs and remove duplication. A repair invoice does not by itself establish responsibility, necessity and recoverability.
    
4.  ### 4. Record the findings and obtain approval
    
    Prepare an itemised assessment showing the allegation, technical basis, supported amount and open questions. Ask the relevant advisers to resolve disputed technical and legal points. Obtain approval before accepting a charge or issuing a claim against your supply chain.
    

**Before you finish:** The resulting schedule should separate responsibility, remedial scope and valuation, with evidence and unresolved issues visible for each.

## Worked example

### The facts

A £38,000 remedial schedule combines replacing damaged panels with repainting an entire floor.

### What happens

1.  The subcontractor checks the claimed defect against their specification, design duties and installation records.
    
2.  A specialist identifies the affected panels and the technically appropriate repair.
    
3.  They check notices and access, then separate the panel work, wider repainting and access costs with supporting records for each.
    
4.  They record disputed responsibility, repair scope and valuation separately, and obtain the appropriate technical, legal and client approvals before accepting a charge.
    

### What this shows

The disputed scope and amounts are visible. The schedule can be challenged or substantiated without assuming that every invoiced cost is recoverable.

For a claim you are making or defending, our [Defects and damage cost defence](<https://www.quantsurv.com/claims#client-types>) service organises and tests the cost evidence alongside your technical specialist and representative.

## Sources

1.  [Defining and managing defects in ECC and liability for not correcting them (19 June 2023)](<https://www.neccontract.com/news/defining-and-managing-defects-in-ecc-and-liability-for-not-correcting-them>). NEC Contracts.

[Browse dispute resolution and defence in the Library](<https://www.quantsurv.com/library#topic-defence>)

[Browse the Library](<https://www.quantsurv.com/library>)